Renovating an old house: what to check before you demolish

The short answer: before you demolish, check four things. The structure: cracks, damp and the floors. The services: wiring and plumbing are usually replaced entirely. The documents: does the house match its permit and the cadastre. And what you are allowed to change. Load-bearing walls are not opened without an engineer, and changes to the facade, balconies or extensions need a permit.

The check before buying or demolishing

  1. CracksDiagonal cracks from window corners, or cracks that widen, point to foundation movement. Hairline cracks in the plaster usually do not.
  2. Floors and roofRotten timber at the bearings, rusted steel in the concrete, a leaking roof. These decide whether the renovation is worth it.
  3. DampOn the ground floor and in walls against the ground. It is solved before any finish.
  4. The paperworkThe title deed, the registered floor plan and the permit. Any difference from them must be resolved before the works.

What stays, what goes

ElementUsuallyNote
Load-bearing wallsstaynew openings only with a structural design
Timber floorsstrengthened or replacedcheck the bearings
Wiringreplacednew earthing and board
Plumbingreplacedold iron pipes corrode
Windowsreplacedwith thermal and acoustic insulation
Roofrepaired or rebuiltwith insulation and waterproofing

The order of works

  1. Design and permitsAn accurate survey, a design and, where needed, a renovation permit. Maintenance works are usually carried out with a prior declaration to the municipality.
  2. Demolition and structureControlled demolition, then the strengthening. No finishes until the structure is safe.
  3. Roof, windows, dampThe house is made weathertight before the services go in.
  4. Services, plaster, floorsPipes and cables before plaster; screed after them; finishes last.

Read next

Frequent questions

Can I remove a wall inside the house?

Only if it is not load-bearing, or with a structural design that replaces it with a beam or frame. In stone or brick houses, most walls are load-bearing.

Does a renovation need a permit?

Changes to the facade, balconies, entrances and small extensions need a renovation permit. Interior works that do not touch the structure are usually done with a prior declaration. Check with the municipality.

Renovate or demolish and rebuild?

It depends on the structure and the permit. If the walls and foundations are sound, renovation usually costs less and keeps the character. If the structure is damaged, a new build may be safer.

How long does it take?

For a 120–200 m² house, 6–12 months of works after the design and permits, depending on the state of the structure.

The architect's advice

Have the survey and the structural check done before you buy. Their cost is small next to a floor that has to be rebuilt.

General guidance. Permit procedures vary by municipality and type of work.